Premium Only Content
Delays in Child Protection Institute DG Khan چائلڈ پروٹیکشن انسٹی ٹیوٹ ڈی جی خان میں تاخیر کی وجوہات
Child Protection Institute DG Khan چائلڈ پروٹیکشن انسٹی ٹیوٹ ڈی جی خان میں تاخیر کی
4.1 8.1 Schedule:
1. The scheme was behind schedule as the physical progress of work was observed to be lesser than the planned progress (Table 8, Figure 5).
• Planned Physical Progress: 90% as of Jan, 2023
• Actual Physical Progress: 65%
• Actual Financial Progress: 73%
At such a pace of work, the project cost and duration may be enhanced by 12% due to differences in the physical and financial progress and variance at completion as illustrated in Table 7 under Earned Value Analysis.
8.2 Cost:
2. The financial utilization of FY-2022-23 is observed to be 0% as shown in Table 5, due to non-utilization released funds under revenue portion of the PC-I which may result in delayed completion of the project.
8.3 Risks and Constraints:
3. The non-utilization of funds under revenue portion of PC-I may result in delayed completion and limited child protection facility in DG Khan.
8.4 Scope
4. The project informatory board required to be fixed at site of work.
5. A water gauge is required to be fixed, as shown in Figure 6.
6. Housekeeping is required while workers are required to provide the PPEs & Finishing works are also needed, as shown in Figure 7.
7. The operational building construction practices required to sustain the building against wearing, as shown in Figure 8.
8. The scrap material is required to be removed through coordination with administration and relevant department, as shown in Figure 9.
9. The expansion joint is required to be repaired while batten boards are needed to be used with steel plates to cover the joint, as shown in Figure 10.
10. The undulations in the plaster finishing are required to be fixed, as shown in Figure 11.
11. The compaction works are required near the ramps of the building, as shown in Figure 12.
12. The electromechanical equipment is required to be stored properly to avoid it wearing, as shown in Figure 13.
13. The efflorescence is required to be fixed while sweet water is needed to be ensured to avoid the efflorescence, as shown in Figure 14.
14. The compaction works are required before laying the tough tiles, as shown in Figure 15.
15. The sustainability and operational strategy of OHR of PHED is required to be formulated in collaboration with Home, PHE departments & local administration, as shown in Figure 16.
8.5 Health, Safety & Environment
16. The workers are required to be provided with Personal Protecting Equipment (PPEs).
17. The safety equipment such as safety ribbons, and safety signs are required to be fixed at the site. Housekeeping needed to be done while proper mobilization with porta cabins is required to be done at the site of work with the provision of safe drinking water to the human resources.
8.6 Quality Control
18. The quality control plans, quality checklists and methodologies are required to be documented at the site of work.
19. The engineering staff of contractor and consultant need to be present at site of work while a field laboratory is required to be established to control quality of work by contractor, consultant and client as well.
20. The observations as presented in the meeting held on 13th January, 2023 (12:00pm) under the chairmanship of Director General (M&E), P&D Board at the meeting room of Deputy Commissioner Office, DG Khan (Annex-A) are needed to be settled and a compliance report is required to be submitted to the office of DG (M&E), P&D Board, Lahore.
21. The data of major quality control tests such as field density test, load test, sieve analysis, compressive strength test, tough tile tests, steel yield strength test and cement quality test etc. could not be found at site. The field laboratory is required to be established and all relevant quality control tests are required to be performed as per standard specifications and proforma table given below.
-
2:26:24
We Like Shooting
18 hours ago $1.18 earnedWe Like Shooting 593 (Gun Podcast)
27.3K -
57:03
Flyover Conservatives
1 day agoJack Hibbs Blasts California Leaders: Must-Watch!; Can Trump Fix the Mess? How Long will it Take? - Dr. Kirk Elliott | FOC Show
51.1K7 -
2:00:50
DillyDillerson
5 hours agoTalking to the moon!! Just some live views of the FULL MOON!!
32.2K11 -
1:29:29
Glenn Greenwald
9 hours agoWith Biden Out, U.S. Finally Admits Harms of His Israel / Gaza Policy; Biden Pays Homage To George W. Bush; Insane Women’s Tennis Scandal: An “Abusive” Coach | SYSTEM UPDATE #388
67.6K88 -
3:12:23
Danny Polishchuk
11 hours agoWho's To Blame For LA Fires, Jewish Tunnels Update + Forbidden Anthropology
29.7K4 -
1:08:10
Donald Trump Jr.
11 hours agoOne Week Until Inauguration, Live with Rep Anna Paulina Luna & Sen Tommy Tuberville
130K201 -
1:00:13
The StoneZONE with Roger Stone
8 hours agoLAWFARE! Are Trump's Legal Assaults Winding Down? w/ Impeachment Lawyer David Schoen | The StoneZONE
38.7K -
1:01:43
Patriots With Grit
1 day agoShocking Changes Are Coming-7 ‘Mission Critical’ Steps Soon To Be Released That Will Leave You Speechless! | John Richardson
18.7K1 -
8:00:59
Dr Disrespect
14 hours ago🔴LIVE - DR DISRESPECT - MARVEL RIVALS - TOP 500 IN THE WORLD
158K30 -
54:46
LFA TV
1 day agoThe Soon-Coming Social Millennium | TRUMPET DAILY 1.13.25 7pm
31.3K3