requires the project to be completed two months ahead of schedule.

2 years ago

progress models performance measurement progress benchmarks expert judgement
52. In activity definition, work packages are systematically broken down into smaller components called: control accounts (ontrolount) resource breakdown structures (RS) planning portfolios (PlnningPkge) planning activities (Sheuletivity) 53. All of the following statements about rolling planning are true except: rolling planning is a progressive refinement of planning Expressions Project planning activities should be at the same level of detail over the life of the project During early strategic planning, activities are only detailed to milestone levels Work to be undertaken in the last one or two reporting periods should be planned in detail as the work in the current period nears completion