Regardless of the method and technique used to prepare the cost budget for the project it is necessary to go through the following three steps to establish a budgeted cost for each work package the total cost of all work packages must not exceed the total cost; to allocate the budgeted cost obtained from the work package allocation to the activities of the work package; to determine the time schedule for each cost and to develop a project cost budget plan.