Operation Management: Workstations: The following table contains information related to the major
saxi753The following table contains information related to the major activities of a given project a) Draw the project network b) Find the critical path c) Find the project completion time Activity Immediate Predecessor Activity Duration (weeks) A --------- 8 B A 5 C A 7 D C 2 E --------- 3 F E 6 G -------- 1 H G 2 I B, D 10 J F, I 8 K H 17 #OperationManagenent #Techniques #Solutions #Answered17 views